KNIGHTS PARK CAMPUS
The Objective:
We were employeed by Overbury for the removal of asbestos in the duct works containing gaskets to the bolted flanges.
Challenges:
At all times we needed to ensure that the exclusion zone was secure and that the Genie life was utlisedto take the weight of the ductwork.
It was really important that before works commence that we checked all the services to ensure that works did not interfere with supplies to rest of the building.
Total cost: £67,000.00
Project length: 2 months
Client: Overbury